| AA_d8bfdf52 | by year-end 2026 | 2026-10-01 | 2026-12-31 | Ministerial approvals for Alcoa's mine operations in Western Australia. | Secures long-term bauxite supply and operational continuity for Alcoa, impacting long-term valuation and sentiment. Delays would be bearish. | Ticker | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_6cec3253 | later in the process (Massena East), progressing two other sites in parallel | 2026-04-24 | 2027-04-24 | Finalization of terms and announcement of monetization for the Massena East smelter site for a data center project, and progress on two other idled sites. | Monetization of idled assets can generate non-operating income, improve capital efficiency, and contribute to the balance sheet, positively impacting valuation and investor sentiment. | Ticker | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_1f609147 | now closely watching for the next directional signal | 2026-04-24 | 2026-12-31 | Announcement or changes in Guinea's bauxite export policy. | Guinea is a major bauxite supplier; changes in its export policy could impact global bauxite supply and prices, affecting Alcoa's bauxite costs and Alumina segment margins. | Theme | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_b25c2a19 | sequentially this year | 2026-04-24 | 2026-12-31 | Actual global aluminum demand growth, particularly in ex-China markets, and the impact of the Middle East conflict on this trajectory. | Stronger demand would support aluminum prices and Alcoa's Aluminum segment profitability, while a further slowdown due to the conflict would be a headwind. | Theme | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_25358db3 | will progress... successfully | 2026-04-24 | 2027-04-24 | Finalization of agreements with Japanese, Australian, and U.S. governments for the gallium project in Western Australia. | Successful progression could unlock new revenue streams and strategic value from critical minerals, enhancing Alcoa's portfolio and potentially attracting government support. | Ticker | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_1121d817 | continue to delever and get into that range, over time working capital should come back out and into cash | 2026-04-24 | 2027-04-24 | Alcoa reaching its target net debt level ($1 billion to $1.5 billion) and announcing subsequent capital allocation plans (e.g., increased shareholder returns, growth investments). | Achieving the debt target provides financial flexibility, potentially leading to increased shareholder returns or value-creating growth opportunities, boosting investor sentiment. | Ticker | 2026-04-16 | earnings_transcript | AA (ticker) |
| AA_1bae68b6 | one to two years for that restart | 2026-04-24 | 2028-04-24 | Alcoa's decision regarding the restart of the fourth line at its Warrick smelter, considering capital requirements, electricity availability, and operational feasibility. | A restart would add 50,000 tons of aluminum capacity, increasing production and revenue, especially in a tight market. However, it requires significant capital and carries execution risk. | Ticker | 2026-04-16 | earnings_transcript | AA (ticker) |
| CENX_e2e5cb29 | in the fourth quarter | 2026-10-01 | 2026-12-31 | Installation of new replacement transformers at Grundartangi Line 2. | This will enable Grundartangi to operate at increased amperage and return to its full normalized production rate, further enhancing Century's overall output and market supply. | Ticker | 2026-08-06 | earnings_transcript | CENX (ticker) |
| CENX_bc49314b | The full benefit will phase in over the balance of the year | 2026-08-01 | 2026-12-31 | Full benefit realization from the TG 4 power generation turbine at Jamalco. | This milestone provides significant cost savings (approximately $20 per ton benefit) and energy self-sufficiency for the Jamalco refinery, improving its cost structure and operational reliability. | Ticker | 2026-08-06 | earnings_transcript | CENX (ticker) |
| CENX_6d56a28e | by the end of the year | 2026-10-01 | 2026-12-31 | Final investment decision (FID) and groundbreaking for the new 750,000 metric ton Oklahoma smelter project | This project, a joint venture with EGA, would more than double total U.S. aluminum production; reaching FID requires finalizing a power contract with PSO and securing project financing. | Ticker | 2026-02-19 | | CENX (ticker) |
| CSTM_ee9b4ea4 | start up by the end of this year (2026). | 2026-01-01 | 2026-12-31 | Launch of the third Airware casthouse at Issoire. | Adds aerospace-capable capacity, potentially lifting margins and enabling expected aerospace growth (ramping in 2027). | Ticker | 2026-02-18 | earnings_transcript | CSTM (ticker) |
| CSTM_a6e71c79 | for 2026, we are targeting adjusted EBITDA, excluding the noncash impact of metal price lag in the range of $780 million to $820 million and free cash flow in excess of $200 million. | 2026-01-01 | 2026-12-31 | Full-year 2026 guidance on adjusted EBITDA (ex-metal price lag) and free cash flow targets. | Sets investor expectations for margin and cash generation; a realization at the high end would support valuation, while missing could weigh on sentiment. | Ticker | 2026-02-18 | earnings_transcript | CSTM (ticker) |
| CSTM_3827a2d1 | modest benefit in 2026 as they support displaced customers from a competitor (Novelis) fire. | 2026-01-01 | 2026-12-31 | Industrial supply disruption at a competitor leading to a market-share and customer-coverage tailwind for Constellium in 2026. | Positive margin and shipment tailwinds if benefit materializes; could support 2026 EBITDA/FCF outlook. | Ticker | 2026-02-18 | earnings_transcript | CSTM (ticker) |
| KALU_26c3cf24 | later this year; reviewing plans to significantly expand capacity | 2026-07-01 | 2026-12-31 | Execution of two major automotive facility outages for equipment repairs and upgrades, and the finalization/initiation of plans to significantly expand capacity for aluminum drive shaft demand. | Successful execution of outages is critical for future operational efficiency and capacity. The capacity expansion, supported by customer commitments, positions the business for future growth in the automotive segment. | Ticker | 2026-04-22 | earnings_transcript | KALU (ticker) |
| KALU_e96963c6 | continuing to see reshoring, continue to elevate here | 2026-04-22 | 2026-12-31 | The actual impact of refined Section 232 tariffs on import competition and the continued elevation of reshoring activity in the domestic market. | A favorable impact from tariffs and increased reshoring could lead to stronger domestic demand, improved pricing environment, and market share gains for Kaiser, particularly in General Engineering. | Theme | 2026-04-22 | earnings_transcript | KALU (ticker) |
| CSTM_a8d3750a | starting to come in 2027 (ramp-up benefits from Airware casthouse). | 2027-01-01 | 2027-12-31 | Airware casthouse ramp benefits begin to materialize as the Issoire expansion contributes. | Could lift aerospace margins and volume, supporting earnings growth in 2027 onward. | Ticker | 2026-02-18 | earnings_transcript | CSTM (ticker) |
| CENX_16ffaead | second half of 2027 | 2027-07-01 | 2027-12-31 | TeraWulf data center at the Hawesville site commences operations | Triggers the potential value realization of Century's 6.8% equity stake and starts the one-year clock on the company's put option to exit the investment. | Ticker | 2026-02-19 | | CENX (ticker) |
| CSTM_1b65fb35 | by 2028. | 2028-01-01 | 2028-12-31 | Vision 2028 targets: €900 million in adjusted EBITDA (excluding metal price lag) and €300 million in free cash flow. | Long-term targets anchor valuation and guide capital allocation; meeting or exceeding could drive multiple expansion. | Ticker | 2026-02-18 | earnings_transcript | CSTM (ticker) |